As prescribed in 236.570(b)(4), use the following provisions and clauses in fixed-price construction contracts and solicitations as applicable if the solicitation's bid schedule contains one or more items subject to statutory cost limitations, and if a waiver has not been granted (FAR 36.205).
COST LIMITATION (JAN 1997)
(a) Certain items in this solicitation are subject to statutory cost limitations. The limitations are stated in the Schedule.
(b) An offer which does not state separate prices for the items identified in the Schedule as subject to a cost limitation may be considered nonresponsive.
(c) Prices stated in offers for items subject to cost limitations shall include an appropriate apportionment of all costs, direct and indirect, overhead, and profit.
(d) Offers may be rejected which—
(1) Are materially unbalanced for the purpose of bringing items within cost limitations; or
(2) Exceed the cost limitations, unless the limitations have been waived by the Government prior to award.
(End of provision)
NONE