DFARS 252.234-7001 Notice of Earned Value Management System. Basic (Apr 2008) (Current)

As prescribed in 234.203(1), for cost or incentive contracts valued at $20,000,000 or more, and for other contracts for which EVMS will be applied in accordance with 234.201(1)(iii) and (iv)—(1) Use the provision at 252.234-7001, Notice of Earned Value Management System, instead of the provisions at FAR 52.234-2, Notice of Earned Value Management System – Pre-Award IBR, and FAR 52.234-3, Notice of Earned Value Management System – Post-Award IBR, in the solicitation.

See DoD Class Deviation 2015-O0017, Earned Value Management System Threshold. Effective immediately, the Earned Value Management System (EVMS) compliance review threshold at DFARS 234.201(1)(ii), DFARS provision 252.234-7001, and DFARS clause 252.234-7002 is raised from $50 million to $100 million. This class deviation remains in effect until incorporated in the DFARS or otherwise rescinded.
 

NOTICE OF EARNED VALUE MANAGEMENT SYSTEM (APR 2008)

      (a)  If the offeror submits a proposal in the amount of $50,000,000 or more—

              (1)  The offeror shall provide documentation that the Cognizant Federal Agency (CFA) has determined that the proposed Earned Value Management System (EVMS) complies with the EVMS guidelines in the American National Standards Institute/Electronic Industries Alliance Standard 748, Earned Value Management Systems (ANSI/EIA-748) (current version at time of solicitation).  The Government reserves the right to perform reviews of the EVMS when deemed necessary to verify compliance.

              (2)  If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a)(1) of this provision, the offeror shall submit a comprehensive plan for compliance with the guidelines in ANSI/EIA-748.

                    (i)  The plan shall—

                            (A)  Describe the EVMS the offeror intends to use in performance of the contract, and how the proposed EVMS complies with the EVMS guidelines in ANSI/EIA-748;

                            (B)  Distinguish between the offeror’s existing management system and modifications proposed to meet the EVMS guidelines;

                            (C)  Describe the management system and its application in terms of the EVMS guidelines;

                            (D)  Describe the proposed procedure for administration of the EVMS guidelines as applied to subcontractors; and

                            (E)  Describe the process the offeror will use to determine subcontractor compliance with ANSI/EIA-748.

                    (ii)  The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan.

                    (iii)  The offeror’s EVMS plan must provide milestones that indicate when the offeror anticipates that the EVMS will be compliant with the guidelines in ANSI/EIA-748.

      (b)  If the offeror submits a proposal in an amount less than $50,000,000—

              (1)  The offeror shall submit a written description of the management procedures it will use and maintain in the performance of any resultant contract to comply with the requirements of the Earned Value Management System clause of the contract.  The description shall include—

                    (i)  A matrix that correlates each guideline in ANSI/EIA-748 (current version at time of solicitation) to the corresponding process in the offeror’s written management procedures; and

                    (ii)  The process the offeror will use to determine subcontractor compliance with ANSI/EIA-748.

              (2)  If the offeror proposes to use an EVMS that has been determined by the CFA to be in compliance with the EVMS guidelines in ANSI/EIA-748, the offeror may submit a copy of the documentation of such determination instead of the written description required by paragraph (b)(1) of this provision.

      (c)  The offeror shall identify the subcontractors (or the subcontracted effort if subcontractors have not been selected) to whom the EVMS requirements will apply.  The offeror and the Government shall agree to the subcontractors or the subcontracted effort selected for application of the EVMS requirements.  The offeror shall be responsible for ensuring that the selected subcontractors comply with the requirements of the Earned Value Management System clause of the contract.

(End of provision)
 

None, but  the offeror shall identify the subcontractors (or the subcontracted effort if subcontractors have not been selected) to whom the EVMS requirements will apply.  The offeror and the Government shall agree to the subcontractors or the subcontracted effort selected for application of the EVMS requirements.  The offeror shall be responsible for ensuring that the selected subcontractors comply with the requirements of the Earned Value Management System clause of the contract.

Subcontractor ✖ Contracts ✖ 
✔ >52.234-2 Basic
⚠ <252.234-7001 DEV

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!