FAR 52.214-18 Preparation of Bids-Construction. Basic (Apr 1984) (Current)

As prescribed in 14.201-6(l), insert the provision at 52.214-18, Preparation of Bids—Construction, in invitations for bids for construction work.

Preparation of Bids—Construction (Apr 1984)

(a) Bids must be—

    (1) Submitted on the forms furnished by the Government or on copies of those forms, and

    (2) Manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.

(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including—

    (1) Lump sum bidding;

    (2) Alternate prices;

    (3) Units of construction; or

    (4) Any combination of paragraphs (b)(1) through (b)(3) of this provision.

(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words “no bid” in the space provided for any item on which no price is submitted.

(d) Alternate bids will not be considered unless this solicitation authorizes their submission.

(End of provision)

NONE

Services ✖ Supplies ✖ Subcontractor ✖ Contracts ✖ Construction ✔ Architect-Eng ✖ 

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!