FAR 52.215-9 Changes or Additions to Make-or-Buy Program. Basic (Oct 1997) (Current)

As prescribed in 15.408(a), the contracting officer shall insert the clause at 52.215-9, Changes or Additions to Make-or-Buy Program, in solicitations and contracts when it is contemplated that a make-or-buy program will be incorporated in the contract. If a less economical “make” or “buy” categorization is selected for one or more items of significant value, the contracting officer shall use the clause with— (1) Its Alternate I, if a fixed-price incentive contract is contemplated; or (2) Its Alternate II, if a cost-plus-incentive-fee contract is contemplated.

Changes or Additions to Make-or-Buy Program (Oct 1997)

(a) The Contractor shall perform in accordance with the make-or-buy program incorporated in this contract. If the Contractor proposes to change the program, the Contractor shall, reasonably in advance of the proposed change, (1) notify the Contracting Officer in writing, and (2) submit justification in sufficient detail to permit evaluation. Changes in the place of performance of any “make” items in the program are subject to this requirement.

(b) For items deferred at the time of negotiation of this contract for later addition to the program, the Contractor shall, at the earliest possible time—

    (1) Notify the Contracting Officer of each proposed addition; and

    (2) Provide justification in sufficient detail to permit evaluation.

(c) Modification of the make-or-buy program to incorporate proposed changes or additions shall be effective upon the Contractor’s receipt of the Contracting Officer’s written approval.

(End of clause)

NONE

Prime’s Interest;
(Applies when it is contemplated that a make-or-buy program will be incorporated in the contract.);

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.