FAR 52.225-24 Notice of Required Use of American Iron, Steel, and Manufactured Goods-Buy American Statute-Construction Materials Under Trade Agreements. Alt II (Mar 2009) (Current)

As prescribed in 25.1102(e),   

           (1) When using funds appropriated under the Recovery Act for construction, use provisions and clauses 52.225-21, 52.225-22, 52.225-23, or 52.225-24 (with appropriate Alternates) in lieu of the provisions and clauses 52.225-9, 52.225-10, 52.225-11, or 52.225-12 (with appropriate Alternates), respectively, that would be applicable as prescribed in paragraphs (a) through (d) of this section if Recovery Act funds were not used.

           (2) If these Recovery Act provisions and clauses are only applicable to a project consisting of certain line items in the contract, identify in the schedule the line items to which the provisions and clauses apply.

           (3) When using clause 52.225-23, list foreign construction material in paragraph (b)(3) of the clause as follows:

                (i) Basic clause. List all foreign construction materials excepted from the Buy American statute or section 1605 of the Recovery Act, other than manufactured construction material from a Recovery Act designated country or unmanufactured construction material from a designated country.

                (ii) Alternate I. List in paragraph (b)(3) of the clause all foreign construction material excepted from the Buy American statute or section 1605 of the Recovery Act, other than-

                     (A) Manufactured construction material from a Recovery Act designated country other than Bahrain, Mexico, or Oman; or

                     (B) Unmanufactured construction material from a designated country other than Bahrain, Mexico, or Oman.
 

Alternate II (Mar2009). As prescribed in 25.1102(e), add the definition of "Bahrainian, Mexican, or Omani construction material" to paragraph (a) and substitute the following paragraph (d) for paragraph (d) of the basic provision:

(d) Alternate offers. (1) When an offer includes foreign construction material, except foreign construction material from a Recovery Act designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-23, the offeror also may submit an alternate offer based on use of equivalent domestic or Recovery Act designated country construction material other than Bahrainian, Mexican, or Omani construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer and a separate cost comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-23 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-23 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or Recovery Act designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested-

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.
 

NONE

Prime’s Interest;
Services ✖ Supplies ✖ Contracts ✖ Construction ✔ Architect-Eng ✖ 
⚠ <>52.225-12 Basic