FAR 52.232-9 Limitation on Withholding of Payments. Basic (Apr 1984) (Current)

As prescribed in 32.111(b)(2), the contracting officer shall insert a clause, substantially the same as the clause at 52.232-9, Limitation on Withholding of Payments, in solicitations and contracts when a supply contract, research and development contract, service contract, time-and-materials contract, or labor-hour contract is contemplated that includes two or more terms authorizing the temporary withholding of amounts otherwise payable to the contractor for supplies delivered or services performed.

Limitation on Withholding of Payments (Apr 1984)

If more than one clause or Schedule term of this contract authorizes the temporary withholding of amounts otherwise payable to the Contractor for supplies delivered or services performed, the total of the amounts withheld at any one time shall not exceed the greatest amount that may be withheld under any one clause or Schedule term at that time; provided, that this limitation shall not apply to—

    (a) Withholdings pursuant to any clause relating to wages or hours of employees;

    (b) Withholdings not specifically provided for by this contract;

    (c) The recovery of overpayments; and

    (d) Any other withholding for which the Contracting Officer determines that this limitation is inappropriate.

(End of clause)

NONE

Subcontractor ✖ 

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!