Army 5152.211-9001 Variations in Estimated Quantities-Subline Items. Basic (Dec 2019) (Current)

As prescribed in 5111.703(c)(ii), in addition to the clause at FAR 52.211-18, insert the clause at AFARS 5152.211-9001, Variations in Estimated Quantities—Subline Items, in solicitations and contracts when—

(A) A fixed-price construction contract is contemplated that authorizes a variation in the estimated quantity of unit-priced items; and

(B) Those unit priced items will be subdivided into subline items and separately priced for payment purposes.
 

VARIATIONS IN ESTIMATED QUANTITIES — SUBLINE ITEMS (DEC 2019) 

This variation in estimated quantities clause is applicable only to item Nos. ___.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent subline item or elimination of all work under such a second or subsequent subline item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for item Nos. ____ is less than 85% of the quantity of the first subline item listed under such item, the contractor will be paid at the contract unit price for that subline item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause at Federal Acquisition Regulation (FAR) 52.211-18, Variation in Estimated Quantities.

(c) If the actual quantity of work performed under item Nos. ____ exceeds 115% or is less than 85% of the total estimated quantity of the subline item under that item and/or if the quantity of the work performed under the second subline item or any subsequent subline item under item Nos.____ exceeds 115% or is less than 85% of the estimated quantity of any such subline item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.

(End of clause)

NONE

Services ✖ Supplies ✖ Construction ✔ Architect-Eng ✖ 
⚠ =52.211-18 Basic

52.204-2 Security Requirements.

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications.

52.216-16 Incentive Price Revision-Firm Target.

52.216-2 Economic Price Adjustment-Standard Supplies.

52.216-3 Economic Price Adjustment-Semistandard Supplies.

52.216-4 Economic Price Adjustment-Labor and Material.

52.216-5 Price Redetermination-Prospective.

52.216-6 Price Redetermination-Retroactive.

52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Method).

52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method).

52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method).

52.222-43 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts).

52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment.

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026.

52.229-4 Federal, State, and Local Taxes (State and Local Adjustments).

52.229-6 Taxes-Foreign Fixed-Price Contracts.

52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services.

52.232-31 Invitation to Propose Financing Terms.

52.233-3 Protest after Award.

52.236-2 Differing Site Conditions.

52.242-14 Suspension of Work.

52.242-15 Stop-Work Order.

52.243-1 Changes-Fixed-Price.

52.243-2 Changes-Cost-Reimbursement.

52.243-3 Changes-Time-and-Materials or Labor-Hours.

52.243-4 Changes.

52.243-5 Changes and Changed Conditions.

52.243-7 Notification of Changes.

52.250-5 SAFETY Act-Equitable Adjustment.

252.216-7000 Economic Price Adjustment--Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products.

252.216-7001 Economic Price Adjustment--Nonstandard Steel Items.

252.216-7003 Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government.

252.216-7007 Economic Price Adjustment-Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products-Representation.

252.216-7008 Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government-Representation.

252.217-7003 Changes.

252.217-7027 Contract Definitization.

252.227-7002 Readjustment of Payments.

252.232-7000 Advance Payment Pool.

252.232-7012 Performance-Based Payments–Whole-Contract Basis.

252.232-7013 Performance-Based Payments—Deliverable-Item Basis.

252.236-7003 Payment for Mobilization and Preparatory Work.

252.236-7004 Payment for Mobilization and Demobilization.

252.237-7023 Continuation of Essential Contractor Services .

252.239-7004 Orders for Facilities and Services.

252.241-7000 Superseding Contract.

252.243-7001 Pricing of Contract Modifications.

252.243-7002 Requests for Equitable Adjustment.

252.247-7000 Hardship Conditions.

252.247-7002 Revision of Prices.

252.249-7000 Special Termination Costs.

252.215-7015 Program Should-Cost Review.

252.232-7015 Performance-Based Payments—Representation.

252.232-7016 Notice of Progress Payments or Performance-Based Payments.

1852.215-79 Price Adjustment for "Make-or-Buy" Changes.

1852.242-72 Denied Access to NASA Facilities

1852.243-72 Equitable Adjustments.

5252.211-9503 LEVEL OF EFFORT (COST REIMBURSEMENT) (NAVAIR)(DEC 2012)

5252.243-9505 ENGINEERING CHANGES (NAVAIR)

5252.227-9505 TECHNICAL DATA AND COMPUTER SOFTWARE IDENTIFICATION IN ENGINEERING CHANGE PROPOSALS (ECPs) (NAVAIR)

5252.216-9200 Payment of Fixed Fee (Completion Type)

5252.216-9201 Payment of Fixed Fee Based on Staff-hours (Term Type)

5252.216-9205 Fee Determination and Payment (Indefinite Delivery Type Contracts)

5252.217-9201 Contract Maximum Amount

5252.242-9515 RESTRICTION ON THE DIRECT CHARGING OF MATERIAL (VARIATION)

3052.216-70 Evaluation of offers subject to an economic price adjustment clause.

3052.216-71 Determination of award fee.

3052.231-70 Precontract costs.

5152.237-9000 Adjustments to Contractor’s Coefficient for Option Years (Job Order Contracts).

552.236-11 Use and Possession Prior to Completion.

552.236-79 Construction-Manager-As-Constructor.

552.216-71 Economic Price Adjustment—Special Order Program Contracts.

552.238-81 Price Reductions.

552.243-71 Equitable Adjustments.

552.246-70 Source Inspection by Quality Approved Manufacturer.

552.246-77 Additional Contract Warranty Provisions for Supplies of a Noncomplex Nature.

552.270-10 Failure in Performance.

552.238-117 Price Adjustment—Failure To Provide Accurate Information.

552.238-120 Economic Price Adjustment—Federal Supply Schedule Contracts.

552.238-82 Modifications (Federal Supply Schedules).

652.216-71 Price Adjustment.

652.237-70 Compensatory Time Off.

652.237-72 Observance of Legal Holidays and Administrative Leave.

952.204-76 Conditional payment of fee or profit-safeguarding restricted data and other classified information.

952.208-70 Printing.

952.216-7 Allowable cost and payment.

952.216-15 Predetermined indirect cost rates.

952.223-76 Conditional payment of fee or profit-safeguarding restricted data and other classified information and protection of worker safety and health.

970.5211-1 Work authorization.

970.5215-1 Total available fee: Base fee amount and performance fee amount.

970.5215-3 Conditional Payment of Fee, Profit, and Other Incentives-Facility Management Contracts

970.5215-4 Cost reduction.

970.5215-5 Limitation on fee.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!