NASA 1852.243-72 Equitable Adjustments. Basic (APR 1998) (Current)

As prescribed in 1843.205-70(b), the contracting officer may insert a clause substantially as stated at 1852.243-72, Equitable Adjustments, in solicitations and contracts for—
(1) Dismantling, demolishing, or removing improvements; or
(2) Construction, when the contract amount is expected to exceed the simplified acquisition threshold and a fixed-price contract is contemplated.

EQUITABLE ADJUSTMENTS (APR 1998)

(a) The provisions of all other clauses contained in this contract which provide for an equitable adjustment, including those clauses incorporated by reference with the exception of the “Suspension of Work” clause (FAR 52.242-14), are supplemented as follows:

Upon written request, the Contractor shall submit a proposal for review by the Government. The proposal shall be submitted to the contracting officer within the time limit indicated in the request or any extension thereto subsequently granted. The proposal shall provide an itemized breakdown of all increases and decreases in the contract for the Contractor and each subcontractor in at least the following detail: material quantities and costs; direct labor hours and rates for each trade; the associated FICA, FUTA, SUTA, and Workmen’s Compensation Insurance; and equipment hours and rates.

(b) The overhead percentage cited below shall be considered to include all indirect costs including, but not limited to, field and office supervisors and assistants, incidental job burdens, small tools, and general overhead allocations. “Commission” is defined as profit on work performed by others. The percentages for overhead, profit, and commission are negotiable according to the nature, extent, and complexity of the work involved, but in no case shall they exceed the following ceilings:

 

Overhead 
(Percent)

Profit 
(Percent)

Commission

To Contractor on work performed by other than its own forces

-----

-----

10 percent

To first tier subcontractor on work performed by its subcontractors

-----

-----

10 percent

To Contractor and/or subcontractors on work performed with their own forces

10 percent

10 percent

-----

(c) Not more than four percentages for overhead, profit, and commission shall be allowed regardless of the number of subcontractor tiers.

(d) The Contractor or subcontractor shall not be allowed overhead or commission on the overhead, profit, and/or commission received by its subcontractors.

(e) Equitable adjustments for deleted work shall include credits, limited to the same percentages for overhead, profit, and commission in paragraph (b) of this clause.

(f) On proposals covering both increases and decreases in the amount of the contract, the application of the overhead, profit, and commission shall be on the net change in direct costs for the Contractor or the subcontractor performing the work.

(g) After receipt of the Contractor’s proposal, the contracting officer shall act within a reasonable period, provided that when the necessity to proceed with a change does not permit time to properly check the proposal, or in the event of a failure to reach an agreement on a proposal, the contracting officer may order the Contractor to proceed on the basis of the price being determined at the earliest practicable date. In such a case, the price shall not be more than the increase or less than the decrease proposed.

(End of clause)

NONE

Services ✖ Supplies ✖ Subcontractor ✖ Demolition ✔ Construction ✔ (Applies to n solicitations and contracts for— (1) Dismantling, demolishing, or removing improvements; or (2) Construction, when the contract amount is expected to exceed the simplified acquisition threshold and a fixed-price contract is contemplated.);

52.204-2 Security Requirements.

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications.

52.216-16 Incentive Price Revision-Firm Target.

52.216-2 Economic Price Adjustment-Standard Supplies.

52.216-3 Economic Price Adjustment-Semistandard Supplies.

52.216-4 Economic Price Adjustment-Labor and Material.

52.216-5 Price Redetermination-Prospective.

52.216-6 Price Redetermination-Retroactive.

52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Method).

52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method).

52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method).

52.222-43 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts).

52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment.

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026.

52.229-4 Federal, State, and Local Taxes (State and Local Adjustments).

52.229-6 Taxes-Foreign Fixed-Price Contracts.

52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services.

52.232-31 Invitation to Propose Financing Terms.

52.233-3 Protest after Award.

52.236-2 Differing Site Conditions.

52.242-14 Suspension of Work.

52.242-15 Stop-Work Order.

52.243-1 Changes-Fixed-Price.

52.243-2 Changes-Cost-Reimbursement.

52.243-3 Changes-Time-and-Materials or Labor-Hours.

52.243-4 Changes.

52.243-5 Changes and Changed Conditions.

52.243-7 Notification of Changes.

52.250-5 SAFETY Act-Equitable Adjustment.

252.216-7000 Economic Price Adjustment--Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products.

252.216-7001 Economic Price Adjustment--Nonstandard Steel Items.

252.216-7003 Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government.

252.216-7007 Economic Price Adjustment-Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products-Representation.

252.216-7008 Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government-Representation.

252.217-7003 Changes.

252.217-7027 Contract Definitization.

252.227-7002 Readjustment of Payments.

252.232-7000 Advance Payment Pool.

252.232-7012 Performance-Based Payments–Whole-Contract Basis.

252.232-7013 Performance-Based Payments—Deliverable-Item Basis.

252.236-7003 Payment for Mobilization and Preparatory Work.

252.236-7004 Payment for Mobilization and Demobilization.

252.237-7023 Continuation of Essential Contractor Services .

252.239-7004 Orders for Facilities and Services.

252.241-7000 Superseding Contract.

252.243-7001 Pricing of Contract Modifications.

252.243-7002 Requests for Equitable Adjustment.

252.247-7000 Hardship Conditions.

252.247-7002 Revision of Prices.

252.249-7000 Special Termination Costs.

252.215-7015 Program Should-Cost Review.

252.232-7015 Performance-Based Payments—Representation.

252.232-7016 Notice of Progress Payments or Performance-Based Payments.

1852.215-79 Price Adjustment for "Make-or-Buy" Changes.

1852.242-72 Denied Access to NASA Facilities

5252.211-9503 LEVEL OF EFFORT (COST REIMBURSEMENT) (NAVAIR)(DEC 2012)

5252.243-9505 ENGINEERING CHANGES (NAVAIR)

5252.227-9505 TECHNICAL DATA AND COMPUTER SOFTWARE IDENTIFICATION IN ENGINEERING CHANGE PROPOSALS (ECPs) (NAVAIR)

5252.216-9200 Payment of Fixed Fee (Completion Type)

5252.216-9201 Payment of Fixed Fee Based on Staff-hours (Term Type)

5252.216-9205 Fee Determination and Payment (Indefinite Delivery Type Contracts)

5252.217-9201 Contract Maximum Amount

5252.242-9515 RESTRICTION ON THE DIRECT CHARGING OF MATERIAL (VARIATION)

3052.216-70 Evaluation of offers subject to an economic price adjustment clause.

3052.216-71 Determination of award fee.

3052.231-70 Precontract costs.

5152.211-9001 Variations in Estimated Quantities-Subline Items.

5152.237-9000 Adjustments to Contractor’s Coefficient for Option Years (Job Order Contracts).

552.236-11 Use and Possession Prior to Completion.

552.236-79 Construction-Manager-As-Constructor.

552.216-71 Economic Price Adjustment—Special Order Program Contracts.

552.238-81 Price Reductions.

552.243-71 Equitable Adjustments.

552.246-70 Source Inspection by Quality Approved Manufacturer.

552.246-77 Additional Contract Warranty Provisions for Supplies of a Noncomplex Nature.

552.238-82 Modifications (Federal Supply Schedules).

552.270-10 Failure in Performance.

552.238-117 Price Adjustment—Failure To Provide Accurate Information.

552.238-120 Economic Price Adjustment—Federal Supply Schedule Contracts.

652.216-71 Price Adjustment.

652.237-70 Compensatory Time Off.

652.237-72 Observance of Legal Holidays and Administrative Leave.

952.208-70 Printing.

952.216-7 Allowable cost and payment.

952.227-9 Refund of royalties.

970.5232-5 Liability with respect to cost accounting standards.

970.5211-1 Work authorization.

970.5215-1 Total available fee: Base fee amount and performance fee amount.

970.5215-3 Conditional Payment of Fee, Profit, and Other Incentives-Facility Management Contracts

970.5215-5 Limitation on fee.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!