DFARS 252.236-7003 Payment for Mobilization and Preparatory Work. Basic (Jan 1997) (Current)

As prescribed in 236.570(b)(2), when the head of the contracting activity has approved use of a separate bid item for mobilization and preparatory work, use Use this clause for major construction contracts that require— (A) Major or special items of plant and equipment; or (B) Large stockpiles of material which are in excess of the type, kind, and quantity which would be normal for a contractor qualified to undertake the work. (i) 252.236-7003, Payment for Mobilization and Preparatory Work. Use this clause for major construction contracts that require— (A) Major or special items of plant and equipment; or (B) Large stockpiles of material which are in excess of the type, kind, and quantity which would be normal for a contractor qualified to undertake the work.

PAYMENT FOR MOBILIZATION AND PREPARATORY WORK (JAN 1997)

      (a)  The Government will make payment to the Contractor under the procedures in this clause for mobilization and preparatory work under item no. ____________________.

      (b)  Payments will be made for actual payments by the Contractor on work preparatory to commencing actual work on the construction items for which payment is provided under the terms of this contract, as follows—

              (1)  For construction plant and equipment exceeding $25,000 in value per unit (as appraised by the Contracting Officer at the work site) acquired for the execution of the work;

              (2)  Transportation of all plant and equipment to the site;

              (3)  Material purchased for the prosecution of the contract, but not to be incorporated in the work;

              (4)  Construction of access roads or railroads, camps, trailer courts, mess halls, dormitories or living quarters, field headquarters facilities, and construction yards;

              (5)  Personal services; and

              (6)  Hire of plant.

      (c)  Requests for payment must include—

              (1)  An account of the Contractor's actual expenditures;

              (2)  Supporting documentation, including receipted bills or copies of payrolls and freight bills; and

              (3)  The Contractor's documentation—

                    (i)  Showing that it has acquired the construction plant, equipment, and material free from all encumbrances;

                    (ii)  Agreeing that the construction plant, equipment, and material will not be removed from the site without the written permission of the Contracting Officer; and

                    (iii)  Agreeing that structures and facilities prepared or erected for the prosecution of the contract work will be maintained and not dismantled prior to the completion and acceptance of the entire work, without the written permission of the Contracting Officer.

      (d)  Upon receiving a request for payment, the Government will make payment, less any prescribed retained percentage, if—

              (1)  The Contracting Officer finds the—

                    (i)  Construction plant, material, equipment, and the mobilization and preparatory work performed are suitable and necessary to the efficient prosecution of the contract; and

                    (ii)  Preparatory work has been done with proper economy and efficiency.

              (2)  Payments for construction plant, equipment, material, and structures and facilities prepared or erected for prosecution of the contract work do not exceed—

                    (i)  The Contractor's cost for the work performed less the estimated value upon completion of the contract; and

                    (ii)  100 percent of the cost to the contractor of any items having no appreciable salvage value; and

                    (iii)  75 percent of the cost to the contractor of items which do have an appreciable salvage value.

      (e)(1)  Payments will continue to be made for item no. _____________, and all payments will be deducted from the contract price for this item, until the total deductions reduce this item to zero, after which no further payments will be made under this item.

              (2)  If the total of payments so made does not reduce this item to zero, the balance will be paid to the Contractor in the final payment under the contract.

              (3)  The retained percentage will be paid in accordance with the Payments to Contractor clause of this contract.

      (f)  The Contracting Officer shall determine the value and suitability of the construction plant, equipment, materials, structures and facilities.  The Contracting Officer's determinations are not subject to appeal.

(End of clause)

NONE

Services ✖ Supplies ✖ Subcontractor ✖ Construction ✔ Architect-Eng ✖ (Applies to major construction contracts.);

52.204-2 Security Requirements.

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications.

52.216-16 Incentive Price Revision-Firm Target.

52.216-2 Economic Price Adjustment-Standard Supplies.

52.216-3 Economic Price Adjustment-Semistandard Supplies.

52.216-4 Economic Price Adjustment-Labor and Material.

52.216-5 Price Redetermination-Prospective.

52.216-6 Price Redetermination-Retroactive.

52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Method).

52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method).

52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method).

52.222-43 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts).

52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment.

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026.

52.229-4 Federal, State, and Local Taxes (State and Local Adjustments).

52.229-6 Taxes-Foreign Fixed-Price Contracts.

52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services.

52.232-31 Invitation to Propose Financing Terms.

52.233-3 Protest after Award.

52.236-2 Differing Site Conditions.

52.242-14 Suspension of Work.

52.242-15 Stop-Work Order.

52.243-1 Changes-Fixed-Price.

52.243-2 Changes-Cost-Reimbursement.

52.243-3 Changes-Time-and-Materials or Labor-Hours.

52.243-4 Changes.

52.243-5 Changes and Changed Conditions.

52.243-7 Notification of Changes.

52.250-5 SAFETY Act-Equitable Adjustment.

252.216-7000 Economic Price Adjustment--Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products.

252.216-7001 Economic Price Adjustment--Nonstandard Steel Items.

252.216-7003 Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government.

252.216-7007 Economic Price Adjustment-Basic Steel, Aluminum, Brass, Bronze, or Copper Mill Products-Representation.

252.216-7008 Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government-Representation.

252.217-7003 Changes.

252.217-7027 Contract Definitization.

252.227-7002 Readjustment of Payments.

252.232-7000 Advance Payment Pool.

252.232-7012 Performance-Based Payments–Whole-Contract Basis.

252.232-7013 Performance-Based Payments—Deliverable-Item Basis.

252.236-7004 Payment for Mobilization and Demobilization.

252.237-7023 Continuation of Essential Contractor Services .

252.239-7004 Orders for Facilities and Services.

252.241-7000 Superseding Contract.

252.243-7001 Pricing of Contract Modifications.

252.243-7002 Requests for Equitable Adjustment.

252.247-7000 Hardship Conditions.

252.247-7002 Revision of Prices.

252.249-7000 Special Termination Costs.

252.215-7015 Program Should-Cost Review.

252.232-7015 Performance-Based Payments—Representation.

252.232-7016 Notice of Progress Payments or Performance-Based Payments.

1852.215-79 Price Adjustment for "Make-or-Buy" Changes.

1852.242-72 Denied Access to NASA Facilities

1852.243-72 Equitable Adjustments.

5252.211-9503 LEVEL OF EFFORT (COST REIMBURSEMENT) (NAVAIR)(DEC 2012)

5252.243-9505 ENGINEERING CHANGES (NAVAIR)

5252.227-9505 TECHNICAL DATA AND COMPUTER SOFTWARE IDENTIFICATION IN ENGINEERING CHANGE PROPOSALS (ECPs) (NAVAIR)

5252.216-9200 Payment of Fixed Fee (Completion Type)

5252.216-9201 Payment of Fixed Fee Based on Staff-hours (Term Type)

5252.216-9205 Fee Determination and Payment (Indefinite Delivery Type Contracts)

5252.217-9201 Contract Maximum Amount

5252.242-9515 RESTRICTION ON THE DIRECT CHARGING OF MATERIAL (VARIATION)

3052.216-70 Evaluation of offers subject to an economic price adjustment clause.

3052.216-71 Determination of award fee.

3052.231-70 Precontract costs.

5152.211-9001 Variations in Estimated Quantities-Subline Items.

5152.237-9000 Adjustments to Contractor’s Coefficient for Option Years (Job Order Contracts).

552.236-11 Use and Possession Prior to Completion.

552.236-79 Construction-Manager-As-Constructor.

552.216-71 Economic Price Adjustment—Special Order Program Contracts.

552.238-81 Price Reductions.

552.243-71 Equitable Adjustments.

552.246-70 Source Inspection by Quality Approved Manufacturer.

552.246-77 Additional Contract Warranty Provisions for Supplies of a Noncomplex Nature.

552.238-82 Modifications (Federal Supply Schedules).

552.270-10 Failure in Performance.

552.238-117 Price Adjustment—Failure To Provide Accurate Information.

552.238-120 Economic Price Adjustment—Federal Supply Schedule Contracts.

652.216-71 Price Adjustment.

652.237-70 Compensatory Time Off.

652.237-72 Observance of Legal Holidays and Administrative Leave.

952.208-70 Printing.

952.216-7 Allowable cost and payment.

952.227-9 Refund of royalties.

970.5232-5 Liability with respect to cost accounting standards.

970.5211-1 Work authorization.

970.5215-1 Total available fee: Base fee amount and performance fee amount.

970.5215-3 Conditional Payment of Fee, Profit, and Other Incentives-Facility Management Contracts

970.5215-5 Limitation on fee.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!