FAR 52.209-4 First Article Approval-Government Testing. Alt II (Sep 1989) (Current)

As prescribed in 9.308-2,

(a)(1) The contracting officer shall insert the clause at 52.209-4, First Article Approval—Government Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require first article approval and that the Government will be responsible for conducting the first article test.

    (2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use the basic clause with its Alternate I.

    (3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use the basic clause with its Alternate II.

(b)(1) The contracting officer shall insert a clause substantially the same as the clause at 52.209-4, First Article Approval—Government Testing, in solicitations and contracts when a cost-reimbursement contract is contemplated and it is intended that the contract require first article approval and that the Government be responsible for conducting the first article test.

    (2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use a clause substantially the same as the clause at 52.209-4, First Article Approval—Government Testing, with its Alternate I.

    (3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use a clause substantially the same as the clause at 52.209-4, First Article Approval—Government Testing, with its Alternate II.

First Article Approval—Government Testing Alternate II (Sept 1989)

[Contracting Officer shall insert details]

(a) The Contractor shall deliver ___unit(s) of Lot/Item ___ within ____ calendar days from the date of this contract to the Government at ______ [insert name and address of the testing facility] for first article tests. The shipping documentation shall contain this contract number and the Lot/Item identification. The characteristics that the first article must meet and the testing requirements are specified elsewhere in this contract.

(b) Within _____ calendar days after the Government receives the first article, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.

(c) If the first article is disapproved, the Contractor, upon Government request, shall submit an additional first article for testing. After each request, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall furnish any additional first article to the Government under the terms and conditions and within the time specified by the Government. The Government shall act on this first article within the time limit specified in paragraph (b) of this clause. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule or for any additional costs to the Government related to these tests.

(d) If the Contractor fails to deliver any first article on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.

(e) Unless otherwise provided in the contract, the Contractor—

  (1) May deliver the approved first article as a part of the contract quantity, provided it meets all contract requirements for acceptance and was not consumed or destroyed in testing; and

  (2) Shall remove and dispose of any first article from the Government test facility at the Contractor’s expense.

(f) If the Government does not act within the time specified in paragraph (b) or (c) of this clause, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.

(g) The Contractor is responsible for providing operating and maintenance instructions, spare parts support, and repair of the first article during any first article test.

(h) Before first article approval, the Contracting Officer may, by written authorization, authorize the Contractor to acquire specific materials or components or to commence production to the extent essential to meet the delivery schedules. Until first article approval is granted, only costs for the first article and costs incurred under this authorization are allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government. If first article tests reveal deviations from contract requirements, the Contractor shall, at the location designated by the Government, make the required changes or replace all items produced under this contract at no change in the contract price.

(i) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the Offeror/Contractor and have been accepted by the Government. The Offeror/Contractor may request a waiver.

(End of clause)

Prime’s Interest;
Services ✖ C/R ✖ Construction ✖ Architect-Eng ✖ (Applies when the contract require first article approval and that the Government will be responsible for conducting the first article test and if it is necessary to authorize the contractor to purchase material or to commence production before first article approval);

52.203-16 Preventing Personal Conflicts of Interest.

52.209-3 First Article Approval-Contractor Testing.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.215-17 Waiver of Facilities Capital Cost of Money.

52.219-18 Notification of Competition Limited to Eligible 8(a) Participants.

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns..

52.219-6 Notice of Total Small Business Set-Aside.

52.219-7 Notice of Partial Small Business Set-Aside.

52.222-36 Equal Opportunity for Workers with Disabilities.

52.225-7 Waiver of Buy American Statute for Civil Aircraft and Related Articles.

52.227-5 Waiver of Indemnity.

52.228-15 Performance and Payment Bonds-Construction.

52.228-4 Workers’ Compensation and War-Hazard Insurance Overseas.

52.232-12 Advance Payments.

52.234-4 Earned Value Management System.

52.237-8 Restriction on Severance Payments to Foreign Nationals.

52.237-9 Waiver of Limitation on Severance Payments to Foreign Nationals.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

252.215-7010 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.

252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies.

252.225-7016 Restriction on Acquisition of Ball and Roller Bearings.

252.225-7019 Restriction on Acquisition of Anchor and Mooring Chain.

252.225-7032 Waiver of United Kingdom Levies-Evaluation of Offers.

252.225-7033 Waiver of United Kingdom Levies.

252.242-7005 Contractor Business Systems.

252.247-7023 Transportation of Supplies by Sea.

252.225-7062 Restriction on Acquisition of Large Medium-Speed Diesel Engines.

252.209-7011 Representation for Restriction on the Use of Certain Institutions of Higher Education.

252.225-7063 Restriction on Acquisition of Components of T-AO 205 and T-ARC Class Vessels.

252.225-7064 Restriction On Acquisition of Certain Satellite Components.

252.270-7001 Pilot Program to Incentivize Contracting with Employee-Owned Businesses—Subcontracting Certification.

252.270-7002 Pilot Program to Incentivize Contracting with Employee-Owned Businesses.

1852.204-76 Security Requirements for Unclassified Information Technology Resources.

1852.227-70 New Technology-Other than a Small Business Firm or Nonprofit Organization.

1852.227-71 Requests for Waiver of Rights to Inventions.

1852.227-88 Government-furnished computer software and related technical data.

1852.228-76 Cross-Waiver of Liability for International Space Station Activities.

1852.228-78 Cross-Waiver of Liability for Science or Space Exploration Activities Unrelated to the International Space Station.

1852.234-2 Earned Value Management System.

1852.245-78 Physical inventory of capital personal property

5252.204-9503 Expediting Contract Closeout (NAVAIR)

5252.209-9513 ORGANIZATIONAL CONFLICT OF INTEREST INSTRUCTIONS (SERVICES) (NAVAIR)

5252.209-9510 ORGANIZATIONAL CONFLICTS OF INTEREST (SERVICES) (NAVAIR)(MAR 2007)

3052.209-70 Prohibition on contracts with corporate expatriates

5152.225-5902 Fitness for Duty and Medical/Dental Care Limitations

652.228-71 Worker’s Compensation Insurance (Defense Base Act) - Services.

752.231-71 Salary supplements for HG employees.

952.209-72 Organizational conflicts of interest.

952.227-84 Notice of right to request patent waiver.

952.250-70 Nuclear hazards indemnity agreement.

952.227-13 Patent rights—acquisition by the Government.

970.5227-9 Notice of Right To Request Patent Waiver

970.5227-10 Patent rights—management and operating contracts, nonprofit organization or small business firm contractor.

970.5227-12 Patent rights-management and operating contracts, for-profit contractor, patent waiver.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!