FAR 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications (DEVIATION 2022-O0001). DEV (Oct 2021) (Current)

Use the following clause, when contracting by negotiation, in lieu of the clause at FAR 52.215-11, Price Reduction for Defective Certified Cost or Pricing Data-Modifications, in solicitations and contracts when it is contemplated that certified cost or pricing data will be required from the contractor or any subcontractor for the pricing of contract modifications and FAR clause 52.215-10, Price Reduction for Defective Certified Cost or Pricing Data, has not been included.

PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA—MODIFICATIONS (DEVIATION 2022-O0001) (OCT 2021)

    (a) This clause shall become operative only for any modification to this contract involving a pricing adjustment expected to exceed $2 million on the date of execution of the 
modification, except that this clause does not apply to any modification if an exception under Federal Acquisition Regulation (FAR) 15.403-1(b) applies.

    (b) If any price, including profit or fee, negotiated in connection with any modification under this clause, or any cost reimbursable under this contract, was increased by any significant amount 
because—

        (1) The Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data; 

        (2) A subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor’s 
Certificate of Current Cost or Pricing Data; or 

        (3) Any of these parties furnished data of any description that were not accurate, the price or cost shall be reduced accordingly and the contract shall be modified to reflect the reduction.  This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause.

    (c) Any reduction in the contract price under paragraph (b) of this clause due to defective data from a prospective subcontractor that was not subsequently awarded the subcontract shall be 
limited to the amount, plus applicable overhead and profit markup, by which—

        (1) The actual subcontract price; or 

        (2) The actual cost to the Contractor, if there was no subcontract awarded, was less than the prospective subcontract cost estimate submitted by the Contractor; provided, that the actual subcontract price was not itself affected by defective certified cost or pricing data.

    (d)(1) If the Contracting Officer determines under paragraph (b) of this clause that a price or cost reduction should be made, the Contractor agrees not to raise the following matters as a defense:

            (i) The Contractor or subcontractor was a sole source supplier or otherwise was in a superior bargaining position and thus the price of the contract would not have been modified even if accurate, complete, and current certified cost or pricing data had been submitted.

            (ii) The Contracting Officer should have known that the certified cost or pricing data in issue were defective even though the Contractor or subcontractor took no affirmative action to bring the character of the data to the attention of the Contracting Officer.

            (iii) The contract was based on an agreement about the total cost of the contract and there was no agreement about the cost of each item procured under the contract.

            (iv) The Contractor or subcontractor did not submit a Certificate of Current Cost or Pricing Data.

        (2)(i) Except as prohibited by subdivision (d)(2)(ii) of this clause, an offset in an amount determined appropriate by the Contracting Officer based upon the facts shall be allowed against the amount of a contract price reduction if—

                (A) The Contractor certifies to the Contracting Officer that, to the best of the Contractor’s knowledge and belief, the Contractor is entitled to the offset in the amount requested; and

                (B) The Contractor proves that the certified cost or pricing data were available before the “as of” date specified on its Certificate of Current Cost or Pricing Data, and that the data were not submitted before such date.

            (ii) An offset shall not be allowed if—

                (A) The understated data were known by the Contractor to be understated before the “as of” date specified on its Certificate of Current Cost or Pricing Data; or

                (B) The Government proves that the facts demonstrate that the contract price would not have increased in the amount to be offset even if the available data had been submitted before the “as of” date specified on its Certificate of Current Cost or Pricing Data.

    (e) If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid—

        (1) Interest compounded daily, as required by 26 U.S.C. 6622, on the amount of such overpayment to be computed from the date(s) of overpayment to the Contractor to the date the Government is repaid by the Contractor at the applicable underpayment rate effective for each quarter prescribed by the Secretary of the Treasury under 26 U.S.C. 6621(a)(2); and

        (2) A penalty equal to the amount of the overpayment, if the Contractor or subcontractor knowingly submitted certified cost or pricing data that were incomplete, inaccurate, or noncurrent.

(End of clause)

 

NONE, but see Paragraph (b). "If any price, including profit or fee, negotiated in connection with any modification under this clause, or any cost reimbursable under this contract, was increased by any significant amount 
because—

        (1) The Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data; 

        (2) A subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor’s 
Certificate of Current Cost or Pricing Data; or 

        (3) Any of these parties furnished data of any description that were not accurate, the price or cost shall be reduced accordingly and the contract shall be modified to reflect the reduction.  This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause."
 

Prime’s Interest;
Commercial items ✖ 
✔ >52.215-11 Basic
⚠ <>52.215-10 Basic

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations.

52.214-27 Price Reduction for Defective Certified Cost or Pricing Data-Modifications-Sealed Bidding.

52.215-10 Price Reduction for Defective Certified Cost or Pricing Data.

52.216-24 Limitation of Government Liability.

52.222-12 Contract Termination-Debarment.

52.222-50 Combating Trafficking in Persons.

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026.

52.228-1 Bid Guarantee.

52.228-8 Liability and Insurance-Leased Motor Vehicles.

52.232-27 Prompt Payment for Construction Contracts.

52.236-23 Responsibility of the Architect-Engineer Contractor.

52.242-3 Penalties for Unallowable Costs.

52.246-16 Responsibility for Supplies.

52.246-18 Warranty of Supplies of a Complex Nature.

52.246-19 Warranty of Systems and Equipment under Performance Specifications or Design Criteria.

52.246-21 Warranty of Construction.

52.247-21 Contractor Liability for Personal Injury and/or Property Damage.

52.247-22 Contractor Liability for Loss of and/or Damage to Freight other than Household Goods.

52.247-23 Contractor Liability for Loss of and/or Damage to Household Goods.

52.247-58 Loading, Blocking, and Bracing of Freight Car Shipments.

252.227-7019 Validation of Asserted Restrictions--Computer Software.

252.227-7037 Validation of Restrictive Markings on Technical Data.

252.247-7007 Liability and Insurance.

252.247-7014 Demurrage.

252.247-7016 Contractor Liability for Loss or Damage.

252.237-7025 Preaward Transparency Requirements for Firms Offering to Support Department of Defense Audits—Representation and Disclosure.

252.237-7026 Postaward Transparency Requirements for Firms that Support Department of Defense Audits.

252.228-7007 Public Aircraft and State Aircraft Operations—Liability.

1852.245-71 Installation-accountable Government Property.

1852.227-88 Government-furnished computer software and related technical data.

1852.228-70 Aircraft Ground and Flight Risk.

1852.228-71 Aircraft Flight Risks.

1852.228-76 Cross-Waiver of Liability for International Space Station Activities.

1852.228-78 Cross-Waiver of Liability for Science or Space Exploration Activities Unrelated to the International Space Station.

1852.228-80 Insurance - Immunity From Tort Liability.

1852.228-81 Insurance - Partial Immunity From Tort Liability.

1852.228-82 Insurance - Total Immunity From Tort Liability.

1852.236-73 Hurricane Plan.

1852.245-72 Liability for Government property furnished for repair or other services.

3052.209-71 Reserve Officer Training Corps and military recruiting on campus.

3052.217-93 Subcontracts (USCG).

3052.217-95 Liability and insurance (USCG).

3052.217-97 Discharge of liens (USCG).

3052.217-99 Department of Labor Safety and Health Regulations for ship repairing (USCG).

3052.217-100 Guarantee (USCG).

3052.222-70 Strikes or picketing affecting timely completion of the contract work.

3052.222-71 Strikes or picketing affecting access to a DHS facility.

5352.223-9001 Health and Safety on Government Installations

5152.225-5900 Arming Requirements and Procedures for Personal Security Services Contractors and Requests for Personal Protection

5152.225-5903 Compliance with Laws and Regulations

5152.228-5900 Government Liability for Non-Tactical Vehicles

5152.225-5902 Fitness for Duty and Medical/Dental Care Limitations

5152.225-5915 CONTRACTOR ACCOUNTABILITY AND PERSONNEL RECOVERY

552.236-73 Subcontracts.

552.211-70 Substantial Completion.

552.211-76 Charges for Packaging, Packing, and Marking.

552.236-80 Accounting Records and Progress Payments.

552.211-89 Non-Manufactured Wood Packaging Material for Export.

552.236-71 Contractor Responsibilities.

552.236-82 Subcontracts.

552.270-7 Fire and Casualty Damage.

652.236-70 Accident Prevention.

1452.204-70 Release of Claims.

1452.236-72 Preservation of historical and archeological data.

1452.228-72 Liability for Loss or Damage - Department of the Interior.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!